Book a demo

RFQ and quote comparison

Three quotes. Who gets the order?

Orbecta puts quotes side by side and next to the market. You see what each quote costs including transport and surcharges, whether the lead time fits your planning and where a supplier deviates from your RFQ.

Book a demo
Quote comparison · RFQ-2026-031 Example · fictional suppliers and illustrative figures

2,400 pcs stainless steel flanges DN50 PN16 · 1.4404 / 316L

RFQ sent 2 Sep 2026 · 3 quotes · needed in week 46 · DAP Rotterdam · certificate 3.1

Advice: quote BB delivers in week 44, before the required week 46. C delivers four weeks late. Based on unit prices, B costs €2,160 more for the whole order.
CriterionQuote AQuote B · adviceQuote C
Unit price€18,40€17,10€16,20
Vs. market price+7,8%+0,2%−5,1%
Lead time6 weeks8 weeks14 weeks · week 50
IncotermDAP RotterdamDAP RotterdamEXW · transport estimated €0.40/pc
Payment term30 days60 days30 days
Price validity30 days60 days14 days
Material surchargeIncludedIncludedSeparate, follows nickel price · amount not stated
Certificate 3.1YesYesNot stated · request confirmation
Total cost €44.160 €41.040 €39.840incl. estimated transport, excl. nickel surcharge
Award advice

Quote B. On unit price B is €2,160 more expensive than C, but B delivers in week 44. C only delivers in week 50, four weeks after your need date. Including estimated transport the difference is €1,200, and C’s nickel surcharge is still open.

B also follows the RFQ terms, is at market level and pays after 60 days. A is 7.8% above market without better terms.

Amounts from the quotes, except transport for C: that is an estimate based on a Rotterdam freight rate.

Before award · still to request
To BDoes the price also apply for call-offs up to delivery, if the 60-day validity expires before then?
To CCan you deliver in week 46, DAP Rotterdam, at a fixed price including material surcharge and 3.1 certificate?
To AYour price is 7.8% above the market price for 316L. Could you revise your quote?

The lowest unit price is not always the cheapest quote.

Every supplier quotes in its own way. Orbecta makes them comparable.

Price next to the market

How does each quote compare with the market price of the material on the quote date?

Stainless 316L · A +7.8%, B +0.2%, C −5.1%

Total cost

What does the quote cost including transport, surcharges and payment terms, not just per piece?

C: EXW + transport €960 + nickel surcharge open

Lead time next to your need

Does the quote meet the date your production needs?

Needed week 46 · C delivers week 50

Terms next to your RFQ

Where does a quote deviate from what you asked: incoterm, validity, certificates, surcharges?

C deviates on 5 points

What you provide.

Your RFQ or specification and the quotes as you receive them: PDF, email or Excel.

What you get back.

Comparison per criterion

All quotes in one overview, even if each has its own structure.

Total cost

Per quote, with transport and surcharges included.

Deviations from your RFQ

Per supplier, so you know what to ask back.

Award advice

With the justification you can use in your award report.

Awarded? Record the agreements and let Orbecta follow them. See Contract monitoring →

Advice you can account for.

More in the Trust Center →

Calculation visible

You see how total cost is built up and which assumptions were used, such as a transport rate for EXW.

Source for the market comparison

The market price names the series and the date each quote was compared against.

You award

The advice is a justification, not a decision. Questions to suppliers are drafts that you send.

Is there an RFQ out?

Bring the quotes to the demo. We’ll put them side by side and next to the market together.

Book a demo